Timeline
|
| 1923 |
|
The first lots in the Lakeside neighborhood are auctioned.
|
| 1928 |
The first lifeguard
(Leroy "Pete" Droppelman) was hired
The first Lakeside swimming and diving meet was held.
Membership had increased to 63.
|
| 1924
- 1930
|
Wooden platforms were built and laid on steel floats and turn boards
were extended down 3' under the water to form the beginning swim
course. Wooden piers are also part of the club's progress.
The wood was taken off at the end of the summer and stored for protection.
Later these wood structures are replaced by concrete.
The property exists under several names including Kaelin's Quarry,
Highland Lake, and Spring Lake before finally settling on Lakeside.
Water is chlorinated by dragging a tow sack around in the water.
Boats were purchased for this purpose, however, other methods were
also used. Llifeguard, George Ochs, admitted to placing powdered
chlorine in his trunk pockets and swimming through the water.
300 small mouth bass were placed in the Lake.
|
1930 - 1945
|
The
gate house was erected in the 1930's and remains a landmark of our
club. The front gate is the club's entrance and used for membership
check-in during the summer months.
A wooden pavilion
is built where the Eckard building now stands.
The first concession
stand is built. It measured 10' x20' and had a dirt floor.
During rain storms the workers had to stand on drink boxes to avoid
the muddy conditions.
All water in the
Lake area was 10 or more feet deep. A wooden crib built on
barrels was erected adjacent to the lake area for the sole purpose
of teaching swim lessons.
A tower is constructed
on the cliff that included a cable and trolley that could be ridden
down into the lake.
The first concrete
pool is built. It was very small and located in the same area
as the current instructional pool is today. The pool was poorly
constructed and had 2 or 3 concrete bottoms placed on top of each
other because of pressure from the water in the lake pushed the
bottoms up.
Because of the new
glider base at Bowman Field, Lakeside members enjoyed daily "glider
shows".
|
| 1946 |
Jack
Thompson is named Secretary-Treasure of the Lakeside Board of Directors |
| 1947 |
The "Lake"
is drained for the first time. |
| 1949 |
The first
chlorination system was installed.
Jack Thompson is
named Lakeside Manager.
|
| 1956 |
First
Pavilion was completed. Membership increased to 1,278. |
| 1967 |
Construction
begins on a new pool. |
| 1972 |
The first
Maintenance Supervisor was hired. |
| 1973 |
A second
floor is built on the Eckard building.
|
| 1980 |
Lakeside hires its first General Manager, Tom Curtin. Prior
to 1980 the duties of a General Manager (long range planning, construction
supervision, bookkeeping, membership, etc.) were handled by various
board members. Jack Thompson's duties included pool management,
supervision of concessions and gate, and swim coach.
|
| 1981 |
A 25-yard
practice area and turn board were completed at the back of the pier.
|
| 1982 |
Construction
begins on a new pavilion. |
| 1983 |
Dedication
of the new pavilion named "The Jack Thompson Swim Pavilion"
The Corporation hires
Brian Cunningham as Maintenance Manager and Mary Tingley Graves
as Aquatic Manager.
|
| 1986 |
The board of Directors resolved to name Jack
Thompson "Mr. Lakeside".
|